A report, received in response to an RTI application said, the Central Vigilance Commission has found alleged financial irregularities in about 16 Games projects costing over two thousand four hundred seventy seven crore rupees. The Commission has found serious procedural lapses and vast differences between the estimated and tendered costs in the development of almost all the Commonwealth Games venues in Delhi. According to an internal investigation report made after inspecting the Games stadia, the Commission has noted wrong justification of rates while procuring items, poor quality of construction, grant of work to ineligible firms, rigged tender process, payment of crores of rupees for non-existent items and use of inferior products.
News On AIR | November 28, 2010 1:48 PM
CVC finds alleged financial irregularities in 16 CWG projects